THE AVRIK PROCESS
How an Avrik Application Runs
From the first site assessment to the completed application. What happens, in what order, and what your site is asked to provide at each stage.
01
Setup
The 25,000 litre application truck is positioned on stable ground at the perimeter. It mixes the product into a homogeneous mix to ensure even application.
Dual 20 bar pumps and motors hold consistent pressure through the run and allow the product to be pumped through the hose to the UGV. Two pump sets mean a single failure does not stop a treatment mid-programme. A water source is required which can be provided via water cart or mains. All product is provided to complete the project prior to start date to ensure continuous application and minimise any potential downtime.

02
Hose reel
A motor driven reel deploys and retrieves up to 1,000 metres of poly hose, up to 4 inches in diameter and rated to 300 PSI, giving controlled, repeatable handling across the full working area.
Hose is run from the truck out to the UGV, and the working area, exclusion zone and operator position are confirmed before the machine moves.
The rig can pump up to 2 km if required, so most TSFs can be worked from a single laydown area.

03
Deploy
The UGV is operated from stable ground outside the treatment area, by two operational personnel. Neither of them stands on the surface being treated. One operates the UGV while the other operates the hose reel.
The UGV imposes as low as 2 psi, depending on track configuration, which is what puts it onto surfaces that will not take a truck. Interchangeable crawler and Archimedes screw tracks extend that reach further again. Track configuration is specified before mobilisation.

04
Application
The UGV applies polymers or mulch products at a precise, consistent rate, with 360 degree spray capability and a reach of 100 metres for uniform coverage across large treatment areas.
Product travels out to the UGV via the hose, so the UGV does not need to return to the laydown to refill, maximising application time.
Typical daily coverage is 20 hectares.

05
Monitor
An automated drone, tethered directly to the UGV for power, gives continuous flight with no battery limits.
It holds station over the working area and gives the operator a view of coverage as it is laid down, rather than after the fact.

PRODUCT SELECTION
Application is only half the problem
Getting product onto a surface is half of what makes a treatment hold. The other half is choosing the right product for the substrate beneath it.
SuppressX and FibreLoc are built for different jobs. SuppressX is a polymer that binds and seals the surface. FibreLoc is a wood fibre mulch that holds a treatment for longer where the surface has to last. Which one suits comes down to the substrate, not the surface type.
Avrik can carry out substrate testing before a programme is scoped, so the product is selected against test results rather than assumption. Application rate and expected treatment life are set from that, for the specific surface.
SAFETY
Two people, and neither of them on the surface
The reason the sequence is built this way is that nobody has to stand on the surface being treated.
The application truck sits on stable ground at the perimeter. The operator works from outside the treatment area. Two operational personnel run the system. The tailings surface carries the bogging, engulfment and rollover risk, and nobody is on it.
The machines working on sites today are remotely operated, with an operator in control of the machine throughout the run.
WHERE TO START
Starting with a trial area
Avrik is happy to begin with a nominated trial area where a site wants one, treated and monitored so coverage, treatment behaviour and durability can be assessed on the site’s own substrate before a full programme is scoped. Substrates vary between facilities, and a trial produces the record the full programme is planned from.
COMMON QUESTIONS
Application process FAQ
What happens first?
A site and surface assessment. Treatment area, surface condition and deposition history, bearing capacity, perimeter access and the dust source actually being controlled. Nothing is quoted or scheduled before that, because the assessment is what decides whether the area can be worked from a stable perimeter at all.
How far from the treatment area can the application truck sit?
The truck can pump up to 2 km. It is positioned on stable ground at the perimeter and product travels out to the machine down the hose, which is what allows the treatment area itself to be ground beyond the safe reach of other plant. Terrain and elevation bear on it, so the specific set-up position is assessed before a programme is committed.
Does the UGV come off the surface to refill?
No. Product is mixed and pumped at the truck and travels out to the machine down the hose, so the machine stays where it is working. The supply reaches the machine rather than the machine reaching the supply.
How many Avrik personnel are on site during a run?
Two operational personnel. Both work from stable ground outside the treatment area. The operator controls the machine remotely and nobody is on the surface being treated.
How much can be treated in a day?
Typical daily coverage is 20 hectares. Actual coverage on a given facility depends on the surface, the treatment specified and the working window, and is set out in the proposal.
Are the machines autonomous or remotely operated?
The machines working on sites today are remotely operated, with an operator in control throughout the run. Autonomous units are in manufacturing and the platform is built toward autonomous operation.
What is the site left with at the end of a programme?
A record of what was treated and where, covering the treated area, the sequence and the timing, for internal reporting and for regulator or community enquiries. Where a programme runs in stages, that record is what the next stage is planned from.